  • Façade works are now complete all the way up to the penthouse floors with only ground floor shopfront glazing remaining. Fit out works across all apartments on both towers are also well advanced including penthouse fit out activities.
  • The common areas are also progressing well including the swimming pool, communal dining areas, rooftop bar and podium sky garden. The eastern façade greenwall has also been completed.
  • The external ground floor eastern plaza works has also seen significant progress during October.

NORTH TOWER

  • Complete install of structural steel to roof
  • Continue roofing install to Level 22
  • Removal of the North Tower Crane from site

LEVEL 7 PODIUM

  • Complete install of structural steel to roof
  • Continue roofing install to Level 22

SOUTH TOWER

  • Compete structural steel install to roof
  • Complete roofing install
  • Removal & build new section of cantilever scaffold for fascia cladding install
  • Continue fascia cladding install
  • Removal of South Tower twin hoist from site
  • The roof steelwork & fascia cladding being completed on both towers
  • Windows being installed up to Level 20 on the North Tower & Level 19 on the South Tower
  • Installation of roof steelwork & commence fascia cladding

NORTH TOWER

  • Install L22 panels
  • Pour L22 Pour 1 & 2 (final pours)
  • Install precast stair cores, fins & fin lid panels on Level 22
  • Form, reo, pour lids to stair cores
  • Continue window installation (up to L17)

SOUTH TOWER

  • Pour L20 Pour 1 & 2 (final pours)
  • Install precast stair cores, lift core lid & fins on Level 20
  • Form, reo, pour lids to stair cores
  • Commence roof structural steelwork installation
Pushing through the cold and rainy weather (usual for June in Adelaide) the West Franklin Residential Development construction team have reached great heights, 60 meters to be exact.

North Tower

  • Precast stair cores & fins were installed from Level 19 - Level 20 & Level 20 - Level 21.
  • Landing of the Level 20 & Level 21 panels & slab pours is now complete
  • The North core lift core from Level 21 - Level 22 & Level 22 - Rooftop have been poured.

South Tower

  • Precast stair cores & fins were installed from Level 18 - Level 19 & Level 19 - Level 20.
  • The panels have been landed from Level 19 & Level 20 and the Level 19 slab has been poured.
  • The final pour & jump of South lift core has been completed
  • The team has now dismantled the South core jumpform.

North Tower

  • Install L17 & L18 panels
  • Pour Level 17 & 18 slabs
  • Install  L17 - L18 & L18 - L19 precast stair cores & fins
  • Jump & pour lift core jumpform L19 - L20 & L20 - L21
  • Installation of Level 7 canopy CFC cladding

South Tower

  • Install L16 & L17 Panels
  • Pour L16, L17 & L18 slabs
  • Install L16 - L17 & L17 - L18 precast stair cores & fins
  • Jump & pour lift core Jumpform L18 - L19 & L19 - L20
  • Install L18, L9, L10 & L11 glass balustrade

North Tower Progress

  • Pouring of the Level 15 slab and installation of precast stair cores & fins to Level 15 and Level 16.
  • The North Core was jumped at Level 18 – Level 19.

South Tower Progress

  • The Level 12 slab was poured and the precast stair cores & fins were installed from Level 12 – Level 15.
  • The precast stair cores & fins were installed at Level 15 – Level 16.
  • Whilst the South Core had two Jumps Level 17 – Level 18 & Level 18 – Level 19.

North Tower

  • Landing Bubbledeck for L12 & L15.
  • The completion of L11 & L12 slab pours and the installation of the precast panels.
  • The jumping & pour of the lift core walls for L15-16 & L16-17.

South Tower

  • Landing of Bubbledeck on L 11 & L12.
  • The completion of L10 & 11 slab pours as well as the installation of the precast panels.
  • The Jumping and pour of the lift core walls for L12-L15 and L15-L16.

CONSTRUCTION UPDATE

  • North Tower Level 9, 10 slab pours
  • North Tower lift core jumpform jump to L15
  • South Tower Level 9 slab pours
  • South Tower lift core jumpform jump to L12
  • Ground Floor slab pours continuing
  • Commence setting out walls in lower levels 2 – 6
  • First fix Services installation in Levels 2 – 6

CONSTRUCTION UPDATE

  • Completion of Level 7 transfer slab (NE corner)
  • Commencement of the split into two towers ( North & South ) at Level 8
  • Erection of Level 8 props & landing of North & South tower L8 panels
  • Pouring of Level 8 slabs

Invest Form

Disclaimer: Terms and Conditions apply to this offer and is only available on pre-selected apartments, subject to availability. This offer is subject to the Purchaser entering into a property managing agreement or similar with Oaks Hotels & Resorts (SA) Pty Ltd for letting services. The circumstances and investment objectives of individuals have not been taken into account and interested persons should rely on their own enquiries. We recommend that you seek independent professional advice, including any taxation implications. It is your sole responsibility to satisfy yourself in the suitability of this offer, and we accept no responsibility or liability in this respect. Moreover, this is a guarantee of rental income for two years. It is not to be implied as to any guarantee of any capital growth. For more information on this limited offer, call West Franklin Apartments on 1300 992 166.